^ Copies of permit application to USACE, RWQCB and BCDC <br />^ Meeting minutes <br />Task 3 -Construction (Inspection Phase) <br />Task 3A -Bid Process (Inspection Phase) <br />Consultant will provide the following during the bid process: <br />^ Attendance at pre-bid meeting <br />^ Preparation of addenda as required <br />^ Answer RFIs during bidding <br />Task 3B -Construction Engineering (Inspection Phase) <br />During this period, Consultant will provide: <br />^ Attendance at preconstruction meeting <br />^ Job site visit and field review (six times) <br />^ Review submittals <br />^ Answer RFIs during construction <br />^ Prepare record drawings based on set provided to the City by the Contractor <br />Consultant Deliverables <br />^ Meeting minutes <br />^ Submittal reviews <br />^ Field visit notes <br />^ RFI responses <br />^ Record drawings <br />Relocate Boat Launch Ramp January 6, 2005 <br />Project. No. 150-38-246 Page 18 of 21 <br />