BID SUMMARY
<br />� y
<br />PROJECT - TITLE: Par Course Improvements
<br />PROJECT NO.: 10- 150 -38-322
<br />BID NO.: 10- 11.026
<br />This document is a summary of bids received for the subject project and are provided
<br />only as a convenience. Listing of a particular bid is not a finding that such bid has
<br />been found to be responsive or accepted as complete by the City. An award of
<br />contract, If any, is subject to approval of the City Council and /or the City Manager.
<br />Contractors should refer to the contract documents for bidding information.
<br />BID OPENING
<br />DATE: Friday, July 1, 2011
<br />TIME: 11:00 AM
<br />LOCATION: City Clerk
<br />ENGINEER'S ESTIMATE -
<br />Date Approved: 6/8/2011
<br />Prepared by: NNC
<br />Blossom Valley Construction
<br />1125 Mabury Road
<br />San Jose, CA 95133
<br />Phone: 408 - 993 -0766
<br />Fax; 408 - 294 -0697
<br />Star Construction, Inc.
<br />240 Allen Drive
<br />San Bruno, CA 94066
<br />Phone: .650-738-0485
<br />Fax: 650 -359 -7763
<br />McGuire and Hester
<br />9009 Railroad Avenue
<br />Oakland, CA 94063
<br />Phone: 510 -632 -7676
<br />Fax: 510 - 562 -5209
<br />ITEM
<br />NO,
<br />QUANTITY
<br />ITEM
<br />UNIT COST
<br />ITEM COST
<br />UNIT COST
<br />ITEM COST
<br />UNIT COST
<br />ITEM COST
<br />UNIT COST
<br />ITEM COST
<br />1
<br />1 LS
<br />Mobilization
<br />$28,640.00
<br />$28,640:00
<br />$9,310.00
<br />$9,310.00
<br />$25,000.00
<br />$25,000.00
<br />$46,160.00
<br />$46,160.00
<br />2
<br />1 LS
<br />Pedestrian Control and Signage
<br />$10,000.00
<br />$10,000.00
<br />$425.00
<br />$425.00
<br />$5,500.00
<br />$5,500.00
<br />$11,600.00
<br />$11,600.00
<br />3
<br />1 LS
<br />Grind and Stockpile Existing AC
<br />$26,000.00
<br />$26,000.00
<br />$23,400.00
<br />$23,400.00
<br />$30,000.00
<br />$30,000.00
<br />$41,800.00
<br />$41,800.00
<br />on site
<br />4
<br />1 LS
<br />Site Grading
<br />$50,000.00
<br />$50,000.00
<br />$48,060.00
<br />$48,060.00
<br />$50,000.00
<br />$50,000.00
<br />$37,700.00
<br />$37,700.00
<br />5
<br />1 LS
<br />Compact AC Grindings as Base
<br />$102,000.00
<br />$102,000.00
<br />$14,400.00
<br />$14,400.00
<br />$40,000.00
<br />$40,000.00
<br />$42,900.00
<br />$42,900.00
<br />6
<br />1,250 TON
<br />Furnish and Install 3" AC
<br />$150.00
<br />$187,500.00
<br />$130.00
<br />$162,500.00
<br />$160.00
<br />$200,000.00
<br />$100.00
<br />$125,000.00
<br />Pavement
<br />7
<br />11,200 LF
<br />Headerboard
<br />$8.00
<br />$89,600.00
<br />$6.30
<br />$70,560.00
<br />$8.00
<br />$89,600.00
<br />$8.00
<br />$89,600.00
<br />8
<br />5,000 SF
<br />Reinforced Concrete Pads
<br />$20.00
<br />$100,000.00
<br />$6.80
<br />$34,000.00
<br />$9.00
<br />$45,000.00
<br />$16.00
<br />$80,000.00
<br />(Exercise Stations)
<br />9
<br />11 EA
<br />Bench
<br />$700.00
<br />$7,700.00
<br />$947.00
<br />$10,417.00
<br />$820.00
<br />$9,020.00
<br />$1,800.00
<br />$19,800.00
<br />10
<br />120 LF
<br />Furnish and Install 4" Irrigation
<br />$11.00
<br />$1,320.00
<br />$9.20
<br />$1,104.00
<br />$60.00
<br />$7,200.00
<br />$17.00
<br />$2,040.00
<br />Sleeves
<br />11
<br />200 CY
<br />Furnish and Install Aggregate
<br />$75.00
<br />$15,000.00
<br />$72.00
<br />$14,400.00
<br />$50.00
<br />$10,000.00
<br />$267.00
<br />$53,400.00
<br />Base
<br />12
<br />200 CY
<br />Furnish and Install Unclassified
<br />$40.00
<br />$8,000.00
<br />$67.00
<br />$13,400.00
<br />$60.00
<br />$12,000.00
<br />$80.00
<br />$16,000.00
<br />Fill
<br />13
<br />40 TON
<br />Offhoul and Dispose AC
<br />$75.00
<br />$3,000.00
<br />$20.00
<br />$800.00
<br />$45.00
<br />$1,800.00
<br />$30.00
<br />$1,200.00
<br />Grindings over 2"
<br />Bid SummaryArm Page 1 of 4 Printed ® 1:15 PM