Laserfiche WebLink
Project History: Opportunities & Obstacles <br />2008 <br />•SL Crossings Masterplan created <br />•State Prop 1C grants awarded ($22 mil) <br />2009 <br />•Planning entitlements approved for Cornerstone <br />• $9.1 mil RDA Set-Aside loan approved <br />2010 •SL Crossings delayed due to economy <br />2011 <br />•Prop 1C deadlines extended <br />•State initiates elimination of redevelopment <br />2012 <br />•Prop 1C issues resolved with State HCD <br />•State DOF demands $3.9 million for BRIDGE <br />2013 <br />•City files lawsuit against DOF and continues to <br />pursue settlement <br />2014 – Cornerstone must start construction to <br />meet Prop 1C expenditure deadline in early 2015