<br />Facility Audit Report 18 <br />San Leandro WWTF <br />6 PROJECT SCHEDULE <br />The proposed schedule for the recommended project is shown in the Table 6.1 below. With <br />prompt approval and sufficient priority, the project should take one year to complete. Loan <br />financing through the California Energy Commission or PG&E could be secured within the time <br />frame indicated between project approval and equipment purchase. <br /> <br /> <br />Table 6.1 San Leandro Aeration Blowers Retrofit Proposed Schedule <br /> <br />Item Description Date <br />Approve Project and Begin Design August 2011 <br />Receive Financing, Purchase Equipment November 2011 <br />Design Completion December 2011 <br />Receive Equipment March 2012 <br />Start Construction April 2012 <br />Construction Completion May 2012 <br />Commissioning Completion June 2012 <br />Energy Savings Verification July 2012 <br />