Laserfiche WebLink
Phase 2 – 7.5 Miles of New <br />Conduit to be constructed in <br />3rd qtr. 2014 <br />•$2.12 million matching EDA grant; <br />total cost to build out $4.3 million <br />•Construction bid and award to be <br />complete July 2014 <br />•Construction scheduled for <br />completion Sept. 2014 <br /> <br /> <br /> <br /> <br /> <br />LitSanLeandro