City of San Leandro <br /> FTA No. 74A0834 <br /> Attachment II <br /> Page 4 of 7 <br /> • Task 1.1:Project Kickoff Meeting.To prepare for a kickoff meeting,the City of San <br /> Leandro will enter into subcontracts with the City of Oakland and RTC. To kick off the <br /> project,City of San Leandro staff will conduct a meeting with City of Oakland staff,RTC, <br /> the San Leandro Creek Alliance and the Caltrans Project Manager to discuss the process, <br /> expectations,roles,and responsibilities.The group will tour and photograph key locations <br /> along the project corridor. <br /> Responsible Party:City of San Leandro,City of Oakland,RTC <br /> • Task 1.2:Project Team Coordination. The Project Team will hold monthly meetings with <br /> Caltrans to provide status updates on the project and ensure that the project remains on <br /> schedule and within budget. <br /> Responsible Party:City of San Leandro <br /> • Task 1.3:Prepare RFP and Select Consultants.The City of San Leandro will provide <br /> Caltrans with a copy of their procurement procedures to ensure compliance with grant <br /> guidelines.The Project Team will prepare a Request for Proposals(RFP)for the selection <br /> and hiring of a planning/engineering team with expertise in trail design,including <br /> consideration for meeting or exceeding Caltrans'disadvantaged business enterprise goals. <br /> 'The Project Team and other review panel members(including a representative of the San <br /> Leandro Creek Alliance)will review proposals,conduct interviews as necessary,and select a <br /> consultant. The City of San Leandro will contract with the selected Consultants. <br /> Responsible Party:City of San Leandro,City of Oakland,RTC <br /> • Task 1.4:Data Collection and Analysis.Working with the Technical Advisory Committee, <br /> the Consultant will identify,research,collect,organize and evaluate information for the study <br /> area including demographic profile of the population in the vicinity of the corridor,relevant <br /> traffic and accident data,the City of San Leandro and City of Oakland General Plans,and <br /> other local and regional plans. <br /> Responsible Party:Consultants <br /> • Task 1.5:Prepare Base Maps.The Consultant will coordinate with the City of San <br /> Leandro,City of Oakland,and other key agencies to prepare base maps of the San Leandro <br /> Creek corridor. The consultant may also prepare a series of physical analysis maps and <br /> drawings at both macro and micro scales to assist in identifying design constraints and <br /> opportunities. <br /> Responsible Party:Consultants <br /> Tasks Deliverables <br /> Task 1.1 Agenda,lists.of contacts,digital photos. <br /> Task 1.2 Notes summarizing meeting. <br /> Task 1.3 RFP,subcontracts. <br /> Task 1.4 . With guidance from the Project Team,assemble and review relevant plans, <br /> documentation collected through previous outreach. <br /> Task 1.5 Base maps,including property boundaries and ownership,existing public <br /> access points,streets along the creek corridor,and initial creek bed and bank <br /> location. <br />