File Number: 17-174 <br />Previously Completed Conduit Installations through a Separate Contract <br />$2,104,909.35 <br />Design, Bid and Award $ 46,812.00 <br />Cost of this Contract $ 427,830.00 <br />Construction Management, Inspection, and Contingency $ 136,122.50 <br />Total Estimated Cost of Project $2,715,673.85 <br />The subject contract is in the amount of $ 427,830.00. If change orders are needed, the <br />maximum authorized total contract amount by this action is $534,787.50. Change orders that <br />increase the project cost beyond the budget authority will not be issued without Council <br />approval of an additional appropriation. <br />Budget Authority <br />The funding for the entire project is as follows: <br />Account No. Source. & Approp. Date Approp. Amount Funds Available <br />150-38-347 EDA Grant, FY 2012-13 $2,121,000.00 $ 133,000.00 <br />120-38-347 DFSI, FY 2012-13 $ 150,000.00 $ 0.00 <br />210-38-347 CIP Fund, FY 2012-13 $ 352,000.00 $ 336,000.00 <br />120-28-196 DFSI, FY 2016-17 $ 491,000.00 $ 491,000.00 <br /> Subtotal $3,114,000.00 $ 960,000.00 <br />ATTACHMENTS <br />·Bid Summary - Fiber Conduit Network Extension Project <br />PREPARED BY: John O’Driscoll, Associate Engineer, Engineering and Transportation <br />Department <br />Page 4 City of San Leandro Printed on 4/24/2017 <br />138