Project Schedule <br />•Early 2018 –Complete 90% design <br />•Spring 2018 –Final design and construction bidding <br />•July 2018 –Construction contract award <br />•Fall 2018 –Start construction of Phase 1 (South Offices) <br />•Early 2019 –Start construction of Phase 2 (Public Safety Building) <br />•Summer 2019 –Substantial completion of construction <br />102