<br /> 175 <br />Phase 1 – 2 Combined Using Magellan Advisors Business <br />Recommendations <br />Summary: <br />Total funding required is $30,785,000 which includes: <br />All existing costs for Phase 1 - $3,500,000 <br />Network costs for new construction for Phase 2 - $9,678,000 <br />Lateral costs ($6,000 per sub X 30% take rate) - $12,720,000 <br />DWDM and Inside Plant Costs - $1,010,000 <br />Total Businesses for Phase 1 – 2 <br />• Phase 1 – 3,028 <br />• Phase 2 – 2,782 <br />Total 5,836 <br />• 30% over 4-year ramp - 1,750 subs <br /> <br />Total Vertical Assets for Phase 2 <br /> <br />• Phase 2 Vertical Assets – 1,765 <br />7% Take Rate – 123 <br /> <br /> <br />LIT San Leandro San Leandro City <br />Total Businesses (inside the city limits) 1134 7931 <br />Business w/LT 15 employees <br />7458 <br />Business w/GE 15employees <br />473 <br />Business w/GE 15 and LE45 <br />327 <br />Business w/ GT 45 employees <br />146 <br />Business in New Development <br />0 <br />Businesses in 500 ft ext <br />3962 <br />