<br />Amendment No. 4 to Consulting Services Agreement between the 11/16/2020
<br />City of San Leandro and BKF Engineers (MacArthur/Superior Roundabout) Page 2 of 4
<br />3. Exhibit B of the Agreement entitled “Compensation Schedule & Reimbursable Expenses” is
<br />hereby amended to read as follows:
<br />
<br />Compensation for the work identified in Exhibit A shall not exceed $164,300.00 as outlined below:
<br />Design Fees – BKF Engineers
<br /> Cost per original contract and
<br />Amendment #1
<br />Amendment
<br />#2 Cost
<br />Amendment
<br />#4 Cost
<br />Task Total
<br />Task 1 – Project Management
<br />and Coordination
<br />$6,211.00 $824.00 $2,008 $9,043.00
<br />Task 2 – Preliminary Studies,
<br />Investigations, and Design
<br />$19,376.00 $2,985.00 $0.00 $22,361.00
<br />Task 3 – Geometric Approval
<br />Drawing
<br />$3,023.00 $0.00 $0.00 $3,023.00
<br />Task 3A – Intersection Design
<br />Alternatives
<br />$11,154.00 $0.00 $0.00 $11,154.00
<br />Task 4 – 70% PS&E $22,776.00 $6,690.00 $0.00 $29,466.00
<br />Task 5 – 100% PS&E $11,243.00 $1,869.00 $0.00 $13,112.00
<br />Task 6 – Final PS&E $8,641.00 $1,057.00 $0.00 $9,698.00
<br />Task 7 – Right-of-way
<br />Surveying and Mapping
<br />$0.00 $22,101.00 $14,958 $37,059.00
<br />Subtotal (BKF Engineers): $82,424.00 $35,526.00 $16,966 $134,916.00
<br />Design Fees – Harris Design
<br /> Cost per original contract and
<br />Amendment #1
<br />Amendment
<br />#2 Cost
<br />Amendment
<br />#4 Cost
<br />Task Total
<br />Task 1 – Project Management
<br />and Coordination
<br />$2,250.00 $0.00 $0.00 $2,250.00
<br />Task 2 – Preliminary Studies,
<br />Investigations, and Design
<br />$1,190.00 $0.00 $0.00 $1,190.00
<br />Task 3 – Geometric Approval
<br />Drawing
<br />$4,900.00 $0.00 $0.00 $4,900.00
<br />Task 4 – 70% PS&E $10,085.00 $0.00 $0.00 $10,085.00
<br />Task 4A – Design of Additional
<br />Streetscape, Landscape, and
<br />Irrigation Improvements in
<br />Opportunity Areas**
<br />$0.00 $3,000.00 $0.00 $3,000.00
<br />Task 5 – 100% PS&E $4,555.00 $0.00 $0.00 $4,555.00
<br />Task 6 – Final PS&E $2,240.00 $0.00 $0.00 $2,240.00
<br />Subtotal (Harris Design): $25,220.00 $3,000.00 $0.00 $28,220.00
<br />
<br />Total Design Fees $107,644.00 $38,526.00 $0.00 $163,136.00
<br />
<br />Reimbursable Expenses
<br />(printing, delivery, computer,
<br />plotter, mileage, parking, tolls)
<br />$1,000.00 $164.00 $0.00 $1,164.00
<br />
<br />Total Contract Amount $108,644.00 $38,690.00 $16,966 $164,300.00
<br />
<br />
<br />
<br />
<br />DocuSign Envelope ID: 12FE834C-EBB6-4293-90F6-AB8F1522C246
|