•Pavement and lighting upgrades for critical taxiway at OAK, AIP grant funded (Approx. <br />$30M). <br />•Taxiway rehabilitation is essential to maintain safety operating standards and is usually <br />conducted every 10-15 years. <br />•Construction began in May 2021 and is scheduled to be complete in November 2021. <br />•Project team worked diligently with the contractor to minimize operational and <br />community noise impacts, although some impacts were unavoidable. <br />Taxiway Bravo Rehabilitation