<br />
<br />Compensation for the work identified in Exhibit A of Amendment #5 shall not exceed $397,859 as outlined
<br />below:
<br /> Design Fees – BKF Engineers
<br /> Cost per original contract and
<br />Amendment #1
<br />Amendment
<br />#2 Cost
<br />Amendment
<br />#4 Cost
<br />Amendment #5
<br />Cost
<br />Task Total
<br />Task 1 – Project Management
<br />and Coordination
<br />$6,211.00 $824.00 $2,008 $18,130 $27,173
<br />Task 2 – Preliminary Studies,
<br />Investigations, and Design
<br />$19,376.00 $2,985.00 $0.00 $35,972 $58,333
<br />Task 3 – Geometric Approval
<br />Drawing
<br />$3,023.00 $0.00 $0.00 $3,023
<br />Task 3A – Intersection Design
<br />Alternatives
<br />$11,154.00 $0.00 $0.00 $11,154
<br />Task 4 – 70% PS&E $22,776.00 $6,690.00 $0.00 $29,466
<br />Task 5 – 100% PS&E $11,243.00 $1,869.00 $0.00 $48,042 $61,154
<br />Task 6 – Final PS&E $8,641.00 $1,057.00 $0.00 $9,906 $19,604
<br />Task 7 – Right-of-way
<br />Surveying and Mapping
<br />$0.00 $22,101.00 $14,958 $37,059
<br />Task 8 – Final Ready to List /
<br />PEER PS&E Package
<br />$0.00 $0.00 $0.00 $17,239 $17,239
<br />Subtotal (BKF Engineers): $82,424.00 $35,526.00 $16,966 $129,289 $264,205
<br /> Design Fees – Harris Design
<br /> Cost per original contract and
<br />Amendment #1
<br />Amendment
<br />#2 Cost
<br />Amendment
<br />#4 Cost
<br />Amendment #5
<br />Cost
<br />Task Total
<br />Task 1 – Project Management
<br />and Coordination
<br />$2,250.00 $0.00 $0.00 $0.00 $2,250
<br />Task 2 – Preliminary Studies,
<br />Investigations, and Design
<br />$1,190.00 $0.00 $0.00 $0.00 $1,190
<br />Task 3 – Geometric Approval
<br />Drawing
<br />$4,900.00 $0.00 $0.00 $0.00 $4,900
<br />Task 4 – 70% PS&E $10,085.00 $0.00 $0.00 $0.00 $10,085
<br />Task 4A – Design of Additional
<br />Streetscape, Landscape, and
<br />Irrigation Improvements in
<br />Opportunity Areas**
<br />$0.00 $3,000.00 $0.00 $5,000 $8,000
<br />Task 5 – 100% PS&E $4,555.00 $0.00 $0.00 $0.00 $4,555
<br />Task 6 – Final PS&E $2,240.00 $0.00 $0.00 $0.00 $2,240
<br />Subtotal (Harris Design): $25,220.00 $3,000.00 $0.00 $5,000 $33,220
<br /> Design Fees – Biggs Cardosa Associates
<br />Tasks 1-4 – Structural
<br />Engineering and Wall Type
<br />Selection
<br />$0.00 $0.00 $0.00 $45,500 $45,500
<br /> Design Fees – Parikh Consultants
<br />Tasks 1-4 – Structural
<br />Engineering and Wall Type
<br />Selection
<br />$0.00 $0.00 $0.00 $53,770 $53,770
<br />
<br />Total Design Fees $107,644.00 $38,526.00 $0.00 $233,559 $396,695
<br />
|