My WebLink
|
Help
|
About
|
Sign Out
Home
10D ATS Review
CityHall
>
City Clerk
>
City Council
>
Agenda Packets
>
2023
>
Packet 20230620
>
10D ATS Review
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
3/21/2024 5:53:11 PM
Creation date
6/23/2023 3:33:43 PM
Metadata
Fields
Template:
CM City Clerk-City Council
CM City Clerk-City Council - Document Type
Staff Report
Document Date (6)
6/20/2023
Retention
PERM
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
5
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
DLF PO 57711 <br />Contract Change Order Summary through 8/5/2022 <br />Item Description Cost <br />1 Covid‐19 protocols $89,525 <br />2 Change transformer from above grade to underground due to insufficent clearances $83,477 <br />3 Changes in restroom tile material and pattern requested by SLPD $71,906 <br />4 Revisions to doors and door hardware to provide a complete project $71,704 <br />5 Additional hazmat abatement and termite damage repair to address unforeseen conditions $53,377 <br />6 Added accoustical tile to walls at the new Dispatch center to reduce noise $51,169 <br />7 Added wainscot, equipment anchorage, finishes at South Offices gym as requested by SLPD $43,543 <br />8 Added power and data outlets as requested by SLPD and PW $33,500 <br />9 Revisions to new fire line at the South Offices due to conflicts with window and existing utilities $32,550 <br />10 <br />Replace existing HVAC fan coil at former traffic office to reduce maintenance costs as requested by <br />PW $29,192 <br />11 Reroute/demo existing rain water leaders discovered after demolition phase at South Offices $22,361 <br />12 <br />Demo of footings and other items in conflict with the work South Offices due to unforeseen <br />conditions $19,916 <br />13 Demo of interior soffit in South Offices required but not shown on plans $19,700 <br />14 Added sprinklers to the trash enclosure at the South Offices as required code $15,230 <br />15 Added exterior lighting at South Offices and concrete monument sign as requested by SLPD $15,000 <br />16 Revise floor plan to move restroom 143 in Police Building due to plumbing conflict $14,213 <br />17 Eliminate transom windows Police Building interior wall due to conflict with HVAC $12,861 <br />18 Change electrical floor box type at South Offices open office area due to existing conditions $11,500 <br />19 Add structural support for transaction window at South Offices required but not shown on plans $10,416 <br />20 Revised seismic brackets for support of existing concrete walls due to unforeseen obstructions $10,404 <br />21 Change handrail South Offices ramp from wall mount to post mount to fit existing conditions $9,092 <br />22 Change countertop materials at public lobby from plastic laminate to quartz at the request of SLPD $9,046 <br />23 <br />Added stucco repair of planter walls that were not part of the original scope to provide a complete <br />project $8,728 <br />24 Install additional ceiling/soffit access hatches as required by code $8,690 <br />25 Installation of tackable wall panels at the SLPD open office area missing from plans $8,181 <br />26 Provide a double check backflow preventer for the new fire service line as requested by EBMUD $7,752 <br />27 <br />Additional work to frame around uplights and to relocate existing HVAC to clear skylights at new <br />public lobby $7,654 <br />28 Revise floor plan at new locker rooms of Police Building due to conflict with existing conduits $6,870 <br />29 Added fireblocking at existing walls of South Offices to meet current code $6,517 <br />30 Added exit signs with emergency lighting at South Offices to meet code $6,510 <br />31 <br />Added floor mat at one of the three entrances to the South Offices building to provide a complete <br />project $6,167 <br />32 59 additional items averaging $1100 each $65,640 <br />Total CCO to date $862,391
The URL can be used to link to this page
Your browser does not support the video tag.