<br /> CONTRACT
<br />100 Brush Creek Rd #206, Santa Rosa, CA 95404
<br />Alex Hailey
<br />707.538.3800 | (707) 736-6897
<br />alexh@rossrec.com
<br /> Contract #: 2025-36596
<br />Quote #: 00047866
<br />Quote Name: Marina Park Fabric Replacement
<br />Quote Total: $89,427.51
<br />
<br />100 Brush Creek Rd, #206, Santa Rosa, CA 95404 • 707.538.3800 • www.rossrec.com •
<br /> CA Contractors License #520752 • OR Contractors License #186870 • Tax ID #68-0103540 • DIR 1000003500
<br />Page 4 of 6
<br />6. RIGHT TO STOP WORK:
<br />Ross Recreation shall have the right to stop work if any payment is not made under this Agreement and set credit terms. Ross
<br />Recreation may keep the job idle until all payments due are received. In the alternative, Ross Recreation may, at its option,
<br />terminate the contract and recover from the Contractor or Owner payment for all work executed to the date of such termination.
<br />
<br />7. SITE CONDITIONS:
<br />Installation price quoted for favorable working conditions. If rock, poor soil conditions, a high -water table, unknown obstructions (ie
<br />- old footings, concrete, pipes, conduits, etc), and/or other unforeseen site conditions exist requiring additional materials and labor,
<br />additional charges may be incurred. Ross Recreation is not responsible for any additional costs or delays caused by unforesee n
<br />site conditions, including but not limit ed to contaminated soil, hidden utilities, archaeological findings , or other site conditions.
<br />
<br />8. EXCLUSIONS/CLARIFICATIONS:
<br />Permits, permit fees, licenses, inspections, site work, and any materials or labor unless specifically quoted and included in the
<br />approved scope of work are excluded.
<br />
<br />Mobilization: Labor quoted by Ross Recreation is for one move -in and one move-out mobilization. Delays and/or multiple
<br />mobilizations due to inadequate site prep, project delays, or other reasons will require an additional mobilization fee by Ro ss
<br />Recreation.
<br />
<br />Site Access: Customer must ensure that the site may be accessed by large machinery or equipment (i.e. a Bobcat tractor, lift, etc.)
<br />for use of moving equipment, footing excavation, and performing required installation work. Site access must be free from cur bs,
<br />concrete walkways, fencing, plantings, etc. If such conditions exist, Ross Recreation will do our best to gain access with minimal
<br />damage but will not be responsible for needed repairs made due to limited access to the site.
<br />
<br />Labor/Installation: Ross Recreation will provide materials and installation (if applicable and quoted) only as quoted and per each
<br />manufacturer’s installation specifications, guidelines, and standard footing details. Installation includes the layout of the equipment,
<br />post-footing excavation based on the manufacturer’s standard footing details and specifications, concrete for footings, and
<br />complete assembly/installation of the purchased materials unless stated otherwise.
<br />
<br />Underground Utilities: Services for underground utilities that are not marked by USA or other location services are not the
<br />responsibility of Ross Recreation. If utilities are inadvertently affected and damaged during the installation and completion of Ros s
<br />Recreation's scope of work, Ross Recreation is not liable for repair nor any associated repair costs incurred by footing and/or
<br />excavation work. Scan/X -ray services prior to the start of work to better identify utilities is highly recommend ed.
<br />
<br />The correct and determined location of the equipment/structure(s) is the sole responsibility of the owner or designated archi tect,
<br />engineer or designer of the project. If the relocation of the equipment/structure(s) is required due to unknown site conditio ns,
<br />permits, project approvals or other occurrences, additional costs may be incurred for re -mobilization, new site considerations and
<br />conditions and/or other project specifics.
<br />
<br />Existing ground cover or surfacing materials interfering with the installation will require a change order to include removal and/or
<br />disposal of materials. Landscape repairs are excluded, including irrigation or/and lines interfering with installation.
<br />
<br />Third-party playground equipment inspection/certification to be completed independently from this contract and by others.
<br />
<br />Project Security: Ross Recreation requires that the customer provide a secure site for the materials and installation of equi pment
<br />and surfacing. Ross Recreation is not responsible for providing site security nor safeguarding the worksite and providing mat erials
<br />against theft, vandalism, or other criminal activities unless specifically included in the scope of work. Any costs are the r esponsibility
<br />of the customer/Owner.
<br />
<br />Docusign Envelope ID: 07B37742-8478-43C2-BD88-38BDCEEDF8AE
|