Laserfiche WebLink
6. 75% PS&E Submittal and Review (by others) <br />7. Sediment Sampling, Analysis & Report <br />8. 100% PS&E Submittal and Review (by others) <br />9. Final PSc~E Submittal (by others) <br />10. Secure DMMO Permits/Authorizations <br />11. Bidding & Award <br />l2. Pre-Dredge Hydrographic Survey (by others) <br />13. City Berth Dredging <br />14. Past-Dredge Hydrographic Survey (by others) <br />15. Corps Channel Dredging <br />A-5 CITY TO PROVIDE <br />Late October 2005 <br />Early November 2005 <br />Late November 2005 <br />Late December 2005 <br />Early January 2006 <br />January -March 2006 <br />April 2006 <br />April -July 2006 <br />July 2006 <br />August -November 2006 <br />1. Records and Reference Materials -Including, but not limited to: record drawings <br />of the project areas; high resolution orthophotos; and AutoCAD files of the <br />project areas. If additional information is needed during the course of the project, <br />Consultant shall immediately notify the Project Engineer. <br />2. Assistance by City employees, as needed/requested. <br />A-6 EXCEPTIONS AND LIMITATIONS <br />1. This scope of work does not include payment of any fees to Regulatory or Public <br />Agencies for applications or permits. <br />2. Changes in the Scope of Work will be deemed "Extra Services." Consultant shall <br />secure written approval from the Project Engineer prior to performing Extra <br />Services. Consultant shall be reimbursed for the cost of Extra Services in <br />accordance with Exhibit B. <br />3. The City will contract directly with surveyors to perform the hdrographic and <br />topographic surveys. Consultant will assist the City in scheduling the surveys to <br />maintain the project schedule. <br />San Leandro Marina Chamle] and Berth Dredging July 21, 2005 <br />597-57-200 Page 19 of 21 <br />