Cost and funding break-out and proposed schedule are as follows: <br />Tentative Cost Breakdown (Subject to Change): Cost <br />($ x 1 million) <br />Scoping 1.5 <br />Environmental/Preliminary Engineering 1.5 <br />Design 8.0 <br />Right-of--Way Support and Capital 12.5 <br />Construction Support and Capital 68.0 <br />Total 91.5 <br />Funding: <br />$80.0 million - ACTA Measure B <br />$11.5 million - Cit~o~ayward <br />$91.5 million -Total <br />Tentative Schedule: <br />Scoping <br />Environmental/ <br />Preliminary Engineering <br />Design <br />Right-of--Way Support and Capital <br />Construction Support and Capital <br />Begin End <br />Spring 2003 Spring 2005 <br />Summer 2005 Winter 2006 <br />Summer 2006 Spring 2008 <br />Summer 2006 Winter 2008 <br />Fall 2008 Summer 2011 <br />5 Rev: July 13. 2005 <br />