Project Timeline <br /> Project Timeline <br /> Because of our experience in conducting public opinion surveys, GRA can generally conduct <br /> an entire survey project 111 approximately six weeks — and in some situations preliminary <br /> data can be available much sooner as deadlines require. The table below shows one possible <br /> schedule for completing each of the key tasks for the City of San Leandro resident satisfac- <br /> tion research project. <br /> Task: Dale: <br /> Survey development April 17 -26 <br /> Revisions April 27 -May 10 <br /> Pretest May 11 <br /> Final revisions May 14 -16 <br /> Translation May 17 -24 <br /> Data collection May 25 -30 <br /> Data processing May 31 June 8 <br /> Analysis June 9 -25 <br /> Report due June 26 <br /> Presentation After June 26 <br /> • <br /> ,1 <br /> City °flan lam dro Godbc Research G Analysis <br /> Godbellesenci & A4hds Page 14 <br />