San Leandro Residential Airport Noise Insulation Program <br /> Task Overview and Timeline <br /> December 2005 <br /> Dec 2005 Conduct Bid Open <br /> Dec 2005 Qualify Apparent Lowest Responsible Bidder <br /> January 2006 <br /> Jan 2006 City Council to Award and Execute a Construction Contract <br /> Jan 2006 Conduct Architectural Surveys of Phase 1 Single Family Homes (95 homes) <br /> February 2006 <br /> Feb 2006 Conduct Pre-Construction Conference <br /> Feb 2006 City issues Notice to Proceed to Contractor <br /> Feb 2006 Review and Approve Contractor Submittals <br /> Feb 2006 Schedule and Conduct Measurement Verifications on the 10 Introductory Phase <br /> Homes <br /> Feb 2006 Continue Phase 1 Architectural Surveys <br /> March 2006 <br /> Mar 2006 Continue Phase I Architectural Surveys <br /> Mar 2006 Order Materials for Introductory Phase Homes (takes 8 -10 weeks to receive order) <br />