Regional Measure 2—INITIAL PROJECT REPORT <br /> I. OVERALL PROJECT INFORMATION <br /> A. Project Sponsor/Co-sponsor(s)/Implementing Agency <br /> Project Sponsor: City of San Leandro <br /> Co-Sponsor: San Francisco Bay Area Rapid Transit District(BART) <br /> Implementing Agency: City of San Leandro <br /> B.Project Purpose <br /> This project improves pedestrian acces and increases bicycle parking at the San Leandro BART <br /> station. The project provides increased safety and comfort for pedestrians by installing bulbouts on <br /> West Juana Avenue,a street heavily used to travel to and from the BART station. The <br /> improvements will enhance the pedestrian experience and usability for those that have difficulty <br /> crossing busy city streets. New electronic bicycle lockers will be installed at the BART station to <br /> increase the amount of secure bicycle parking facilities. <br /> C.Project Description(please provide details) <br /> n Project Graphics to be sent electronically with This Application <br /> The project builds from the City of San Leandro's Transit Oriented Development Strategy to improve <br /> connections between the downtown San Leandro BART Station and the community. The project <br /> improves the southern east to west pedestrian connection running along West Juana Avenue for <br /> approximately 1,100 feet. Sidewalk bulbouts and enhanced crosswalk treatment will be added along <br /> West Juana at the intersection of Carpentier, Clarke,and Hays Street. Sidewalk on one side of West <br /> Juana Avenue between San Leandro Boulevard and Carpentier Street will be widened to provide for <br /> comfortable pedestrian travel. Pedestrian level lighting will be extended from the downtown along West <br /> Juana Avenue towards the BART station. <br /> D. Impediments to Project Completion <br /> None <br /> E. Operability <br /> The City will operate and maintain improvements along West Juana Avenue. BART will operate and <br /> maintain improvements made at the San Leandro BART station. <br /> II.PROJECT PHASE DESCRIPTION and STATUS <br /> F. Environmental— Does NEPA Apply: Yes Ej No <br /> This project is categorically exempt from CEQA per section 15301 —minor alteration to existing facilities. <br /> The City of San Leandro has filed a notice of exemption with the Alameda County recorder. <br /> G. Design— <br /> The design of this project will be complete 3/31/2014. <br /> H. Right-of-Way Activities/Acquisition— <br /> The City has requested two rights of entry for construction of sidewalk up to the property line. The <br /> agreements are expected to be executed before the construction contract is awarded; however,the <br /> agreements are merely a convenience as the work can be built without these agreements. <br /> I. Construction/Vehicle Acquisition - <br /> Construction is expected to commence in late summer 2015 <br /> -2 - <br />