SCHEDULE <br /> Kennedy/Jenks estimates that the work for Task 1 could be completed in approximately seven(7) <br /> weeks once authorization to proceed on Task 1 is received; four(4)weeks for Kennedy/Jenks to <br /> prepare the Technical Memorandum,two(2)weeks for City personnel to review and comment on <br /> the Technical Memorandum, and one(1)week for Kennedy/Jenks to complete the Technical <br /> Memorandum. <br /> Kennedy/Jenks estimates that the work for Task 2 could be completed in approximately fourteen <br /> (14)weeks once authorization to proceed on Task 2 is received: five(5)weeks for Kennedy/Jenks <br /> to prepare the 50% submittal;two(2)weeks for City personnel to review and comment on the 50% <br /> submittal;three(3)weeks for Kennedy/Jenks to prepare the 70% submittal;two (2)weeks for City <br /> personnel to review and comment on the 70%submittal; and two (2)weeks for Kennedy/Jenks to <br /> prepare the final submittal. <br /> EXHIBIT A Page 3 of 3 <br /> 6/12/95 WPCP Clarifier No.2 Odor Control <br />