<br />Consulting Services Agreement between City of San Leandro and Last revised 2/21/18 Glass Architects for the Farrelly Pool Replacement Exhibit B – Page 1 of 2
<br />EXHIBIT B COMPENSATION SCHEDULE & REIMBURSABLE EXPENSES Proposed Basic Services Fees will be on a time and materials basis, not to exceed the following:
<br />
<br />discipline concept DD CD Bid CA reimbursable TOTAL
<br />architectural $15,625 $20,830 $43,745 $3,125 $20,830 $7,790 $111,945
<br />aquatics $8,280 $13,950 $23,628 $3,336 $6,702 $500 $56,396
<br />structural $1,440 $3,000 $6,720 $600 $1,800 $240 $13,800
<br />mechanical $2,304 $4,392 $4,392 $1,152 $2,124 $500 $14,864
<br />electrical $3,258 $3,096 $3,744 $1,152 $4,392 $500 $16,142
<br />civil $2,880 $16,380 $12,816 $372 $4,656 $300 $37,404
<br />landscape $3,288 $4,380 $2,916 $696 $696 $200 $12,176
<br />estimator $4,800 $7,200 $2,400 - - - $14,400
<br />TOTALS $41,875 $73,228 $100,361 $10,433 $41,200 $10,030 $277,127
<br />
<br />A purchase order to begin work is anticipated by April 2018. The following is the anticipated
<br />schedule for completion of the project:
<br />
<br />Conceptual Design (30% ) 8 Weeks from notice to proceed
<br />Design Development (70%) 10 Weeks from receipt of comments
<br />Permit Submittal (100%) 10 Weeks from receipt of comments
<br />Final Bid Documents 2 Weeks after permit issuance
<br />Bidding Phase Approximately 6 Weeks
<br />Construction Administration Ongoing during construction period of ten months
<br />(approx.). Projected start of construction with
<br />school break in summer 2019.