<br />Amendment No. 2 to Consulting Services Agreement between the 2/22/2018
<br />City of San Leandro and BKF Engineers (MacArthur/Superior Roundabout) Page 3 of 5
<br />
<br />
<br />3. Exhibit B of the Agreement entitled “Compensation Schedule & Reimbursable Expenses” is
<br />hereby amended to read as follows to reflect the addition of Tasks 4A and 7 and also the increased costs
<br />for other tasks due to the expanded project footprint and new right-of-way impacts to 650 MacArthur
<br />Boulevard:
<br />
<br />Compensation for the work identified in Exhibit A shall not exceed $147,334.00 as outlined below:
<br />
<br />Design Fees – BKF Engineers
<br /> Cost per original
<br />contract and
<br />Amendment #1
<br />Amendment #2
<br />Cost
<br />Task Total
<br />Task 1 – Project Management and Coordination $6,211.00 $824.00 $7,035.00
<br />Task 2 – Preliminary Studies, Investigations,
<br />and Design
<br />$19,376.00 $2,985.00 $22,361.00
<br />Task 3 – Geometric Approval Drawing $3,023.00 $0.00 $3,023.00
<br />Task 3A – Intersection Design Alternatives $11,154.00 $0.00 $11,154.00
<br />Task 4 – 70% PS&E $22,776.00 $6,690.00 $29,466.00
<br />Task 5 – 100% PS&E $11,243.00 $1,869.00 $13,112.00
<br />Task 6 – Final PS&E $8,641.00 $1,057.00 $9,698.00
<br />Task 7 – Right-of-way Surveying and Mapping** $0.00 $22,101.00 $22,101.00
<br />Subtotal (BKF Engineers): $82,424.00 $35,526.00 $117,950.00
<br />Design Fees – Harris Design
<br /> Cost per original
<br />contract and
<br />Amendment #1
<br />Amendment #2
<br />Cost
<br />Task Total
<br />Task 1 – Project Management and Coordination $2,250.00 $0.00 $2,250.00
<br />Task 2 – Preliminary Studies, Investigations,
<br />and Design
<br />$1,190.00 $0.00 $1,190.00
<br />Task 3 – Geometric Approval Drawing $4,900.00 $0.00 $4,900.00
<br />Task 4 – 70% PS&E $10,085.00 $0.00 $10,085.00
<br />Task 4A – Design of Additional Streetscape,
<br />Landscape, and Irrigation Improvements in
<br />Opportunity Areas**
<br />$0.00 $3,000.00 $3,000.00
<br />Task 5 – 100% PS&E $4,555.00 $0.00 $4,555.00
<br />Task 6 – Final PS&E $2,240.00 $0.00 $2,240.00
<br />Subtotal (Harris Design): $25,220.00 $3,000.00 $28,220.00
<br />
<br />Total Design Fees $107,644.00 $38,526.00 $146,170.00
<br />
<br />Reimbursable Expenses (printing, delivery,
<br />computer, plotter, mileage, parking, tolls)
<br />$1,000.00 $164.00 $1,164.00
<br /> Total Contract Amount $108,644.00 $38,690.00 $147,334.00
<br />
<br />**Tasks 4A and 7 were added with CSA Amendment No. 2
<br />1479
|