Laserfiche WebLink
Consulting Services Agreement between City of San Leandro and 3/16/18 <br />Glass Architects for the Family Aquatic Center Competition Pool Exhibit A – Page 4 of 4 <br />A purchase order to begin work is anticipated by May 2018. The following is the anticipated schedule for completion of the project: <br />Design Development (70%) 10 Weeks from receipt of comments <br />Permit Submittal (100%) 10 Weeks from receipt of comments <br />Final Bid Documents 2 Weeks after permit issuance <br />Bidding Phase Approximately 4-6 Weeks <br />Construction Administration Ongoing during construction period of ten months <br />(approx.). Projected start of construction in early 2019. <br />1506