My WebLink
|
Help
|
About
|
Sign Out
Home
9B Consent
CityHall
>
City Clerk
>
City Council
>
Agenda Packets
>
2022
>
Packet 05162022
>
9B Consent
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
5/11/2022 4:21:30 PM
Creation date
5/11/2022 4:21:28 PM
Metadata
Fields
Template:
CM City Clerk-City Council
CM City Clerk-City Council - Document Type
Staff Report
Document Date (6)
5/16/2022
Retention
PERM
Document Relationships
Reso 2022-071 FY 2023 Proposed Projects Gas Tax Fund
(Approved by)
Path:
\City Clerk\City Council\Resolutions\2022
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
6
PDF
View images
View plain text
File Number: 22-289 <br />City of San Leandro In-House Streets Maintenance - FY 2023 <br />LOCATION EX./PROP. PCI EST. LIFE START/COMPLETION <br />Chapel Ct. (Residential); From 6/100 20 years July/July 2022 <br />Chapel Ave to end. Remove and <br />replace asphalt surface (estimate <br />167 tons). <br />Beatty St. (Residential); From 16/100 20 years July/July 2022 <br />Manor Blvd. to 15130 Beatty and <br />From Fargo to Trojan. Remove and <br />replace asphalt surface (estimate <br />750 tons). <br />Wiley St. (Residential); From Manor 20/100 20 years Aug/Aug 2022 <br />to Dayton and Dayton to Trojan. <br />Remove and replace asphalt surface <br />(estimate 844 tons). <br />Hilding Ave. (Residential): From 18/100 20 years Sept/Sept 2022 <br />Williams to Castro. Remove and <br />replace asphalt surface (estimate <br />171 tons). <br />136th Ave. (Residential): From 9/100 20 years Sept/Oct 2022 <br />E. 14th west, to terminus. Remove <br />and replace asphalt surface (estimate <br />518 tons). <br />Thornton St. (Residential): From 27/100 20 years Oct/Nov 2022 <br />E. 14th to Washington. Remove and <br />replace asphalt surface (estimate <br />324 tons). <br />Elsie Ave. (Residential): From 12/100 20 years April/April 2023 <br />Bancroft to San Rafael. Remove and <br />replace asphalt surface (estimate 977 <br />tons). <br />Santa Maria St. (Residential): From 0/100 20 years May/May 2023 <br />Estudillo to Dolores. Remove and <br />replace asphalt surface (estimate <br />457 tons). <br />Pershing Dr. (Residential): From 11/100 20 years May/June 2023 <br />Best to Stoakes. Remove and <br />replace asphalt surface (estimate <br />(495 tons). <br />Please note that all FY 22 projects are anticipated to be completed by June 30, 2022, so no <br />projects are planned to be rolled over into FY 23. <br />Page 4 City of San Leandro Printed on 5/11/2022
The URL can be used to link to this page
Your browser does not support the video tag.
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).