BID SUMMARY
<br />
<br />Phase 1
<br />BID OPENING Azul Works, Inc.Bay Cities Paving & Grading, Inc.DeSilva Gates Construction, LLC
<br />DATE: April 14, 2022 1400 Egbert Avenue 1450 Civic Ct., Bldg. B - #400 11555 Dublin Boulevard
<br />TIME: 3:00 pm San Francisco, CA 94124 Concord, CA 94520 Dublin, CA 94568
<br />LOCATION: City Clerk's Office Phone: (415) 558-1507 Phone: (925) 687-6666 Phone: (925) 829-9220
<br />Fax: (415) 558-1556 Fax: (925) 687-2122 Fax: (925) 803-4263
<br />ITEM
<br />NO.ITEM UNIT COST ITEM COST UNIT COST UNIT COST UNIT COST
<br />Prepared by: N. Castelino
<br />Date Approved: 3/9/2022
<br />ENGINEER'S ESTIMATE
<br />ITEM COST
<br />PROJECT TITLE:
<br />PROJECT NO.:
<br />BID NO.:
<br />QUANTITY
<br />Annual Street Overlay/Rehabilitation 19-21
<br />2020.0050
<br />21-22.009
<br />This document is a summary of bids received for the subject project and are
<br />provided only as a convenience. Listing of a particular bid is not a finding that
<br />such bid has been found to be responsive or accepted as complete by the City.
<br />An award of contract, if any, is subject to approval of the City Council and/or the
<br />City Manager. Contractors should refer to the contract documents for bidding
<br />information.
<br />ITEM COSTITEM COST
<br />12 Adjust Electric Utility Valve Box
<br />and Cover to Grade per Section
<br />301-1.6
<br />1 EA $ 1,200.00 $1,200.00 $980.00 $980.00 $1,600.00 $1,600.00 $3,300.00 $3,300.00
<br />13 Remove Obstructions from
<br />Driveways per Section 300-1.3 10 EA $ 500.00 $5,000.00 $300.00 $3,000.00 $660.75 $6,607.50 $500.00 $5,000.00
<br />14 Remove Existing Storm Drain
<br />Inlet per Section per Section 300-
<br />1.3
<br />3 EA $ 1,500.00 $4,500.00 $2,000.00 $6,000.00 $894.75 $2,684.25 $2,700.00 $8,100.00
<br />15 Remove Existing Storm Drain
<br />Pipe (12" DIA) per Section 300-
<br />1.3
<br />57 LF $ 200.00 $11,400.00 $310.00 $17,670.00 $63.85 $3,639.45 $80.00 $4,560.00
<br />16 Remove Traffic Loop Detectors
<br />per Section 300-1.3 5 EA $ 500.00 $2,500.00 $300.00 $1,500.00 $1,500.00 $7,500.00 $200.00 $1,000.00
<br />17 Remove Traffic Signal Handhole
<br />Box & Cover per Section 300-1.3 2 EA $ 500.00 $1,000.00 $300.00 $600.00 $450.00 $900.00 $450.00 $900.00
<br />18 Remove and Replace Concrete
<br />Driveway Approach per Section
<br />303-5
<br />1,296 SF $ 30.00 $38,880.00 $16.00 $20,736.00 $30.00 $38,880.00 $30.00 $38,880.00
<br />19 Storm Water Curb Inlet per
<br />Section 303-1 2 EA $ 7,000.00 $14,000.00 $6,500.00 $13,000.00 $7,070.00 $14,140.00 $6,500.00 $13,000.00
<br />20 Storm Water 24"x24" Drop Inlet
<br />per Section 303-1 1 EA $ 6,000.00 $6,000.00 $6,000.00 $6,000.00 $4,305.00 $4,305.00 $3,200.00 $3,200.00
<br />21 12" HDPE Storm Drain Pipe (4' to
<br />6' Depth)63 LF $ 300.00 $18,900.00 $320.00 $20,160.00 $218.25 $13,749.75 $720.00 $45,360.00
<br />22 Install Concrete Island with
<br />Vertical Curb per Section 303-5 298 SF $ 35.00 $10,430.00 $18.00 $5,364.00 $50.00 $14,900.00 $50.00 $14,900.00
<br />Bid Summary - Annual Street Overlay Rehabilitation 19-21 Phase 1.xlsx Page 2 of 6 Printed 4/15/2022 @ 1:07 PM
|