Amendment No. 2 to
<br />Consulting Services Agreement between City of San Leandro and Indigo 2/7/2022
<br />For Construction Support for Police Bldg. and South Office Modifications Project Page 2 of 5
<br />3.Exhibit B of the Agreement entitled “Compensation Schedule & Reimbursable Expenses” is
<br />hereby amended to read as follows and to include the attached updated Standard Rate Schedules (rev.
<br />10/5/21):
<br />Compensation for the work identified under Exhibit A shall not exceed $470,050 as outlined below.
<br />Item Description Original
<br />Estimated
<br />Fee
<br />Revised
<br />amounts
<br />(Amendment 1)
<br />Revised
<br />amounts
<br />(Amendment 2)
<br />1 Attend pre-construction meeting $1,440 $1,440 $1,440
<br />2 Review and respond to submittals $73,600 $73,600 $73,600
<br />3 Review and respond to RFIs $90,600 $90,600 $90,600
<br />4 Review and respond to potential change order
<br />requests
<br />$22,720 $22,720 $22,720
<br />5 Issue Architectural Supplemental Instructions $2,160 $2,160 $2,160
<br />6 Participate in weekly construction project
<br />progress meetings via telephone
<br />$17,820 $48,000 $68,000
<br />7 Attend weekly construction project progress
<br />meetings and conduct site observations
<br />$65,760 $65,760 $65,760
<br />8 Quarterly Verified Reports to the Division of
<br />the State Architect
<br />$5,120 $5,120 $8,400
<br />9 Assist with commissioning, demonstration,
<br />and training of various building systems
<br />$10,080 $10,080 $10,080
<br />10 Conduct preliminary investigation and issue
<br />punch list for each construction phase
<br />$26,240 $26,240 $26,240
<br />11 Notice of Substantial Completion for each
<br />construction phase
<br />$1,440 $1,440 $1,440
<br />12 Assist with Notice of Final Completion $360 $360 $360
<br />13 Final project close-out procedures $6,880 $6,880 $6,880
<br />14 Modifications to project documents due to
<br />bidders’ questions
<br />$7,200 $7,200 $7,200
<br />15 Allowance for communications not included
<br />above with the City’s project manager
<br />$32,200 $39,700 $54,700
<br />16 Reimbursable expenses $14,250 $14,250 $14,250
<br />17 Subconsultant mark-up (15%) $16,220 $16,220 $16,220
<br />Total: $394,090 $431,770 $470,050
<br />DocuSign Envelope ID: BCCEBD4A-E512-459F-95C1-AA5749943D86
|