<br />Consultant shall develop plans, specifications, and estimates for one bidding package with add alternates as
<br />listed here.
<br />● Package 1, Zone 1/ Phase 1 Mulford point, Pescador Point, Boat Launch and Zone 2 Shared Parking
<br />(Add Alternate), all as described in the RFP, work shall include:
<br />o Marina demolition & decommissioning including:
<br />▪ Neptune Drive Sea Wall Replacement (Demo wood structure and replace with concrete
<br />seawall)
<br />▪ Sea Plane Launch and coastal zone immediately south towards El Torito
<br />(Demo/Rebuild Shoreline)
<br />▪ Pescador Boat Lift (Demo)
<br />▪ Pescador Boat Ramp (Demo/Rebuild shoreline)
<br />▪ Fishing Pier (Demo)
<br />o Landside Demolition
<br />o Rip Rap Extension
<br />o Grading and sea level rise mitigation
<br />o Interim Bay Trail
<br />o Shared Parking lot
<br />o Utility Coordination
<br />o Hydroseed or similar ground surface treatment
<br />o Pescador Point restroom and boat launch
<br />
<br />Work shall include but not be limited to the following tasks required to complete the overall scope of work
<br />described herein.
<br />Subtask 3.1 – 50% Design Development
<br />● Prepare the 50% Design Development Plans and Estimates based on the Marina Decommissioning
<br />report, Coastal Engineering report, Conceptual Design for Shoreline Improvements, data collection,
<br />project goals and project budget.
<br />● Develop a utility and infrastructure Masterplan which documents the electrical (EV chargers,
<br />Lighting), data, dry utility, City fiber backbone, wet utilities and irrigation needs for project packages
<br />2, 3 and 4. Detailed utility plans, profiles and calculations are excluded. This plan shall provide the
<br />sizing, inverts, and conforms required for Bid Package 1 (zones 1 and 2, and key areas of zones 3 and
<br />4 identified in Attachment E) to support the park expansion in future phases.
<br />● Coordinate all work including: limits of work, temporary pedestrian access, construction access,
<br />lagoon demo access, existing elements to remain, demolition, surcharging, grading, utilities and
<br />services, future utility connections, and perimeter conforms f or each package.
<br />● Coordinate conforms of adjacent private development including perimeter conforms, construction
<br />phasing, development schedule, Interim access as described in Subtask 3.5, surcharging, sea level rise
<br />mitigation, grading and drainage, wet and dry utilities, fire access, garbage access, lighting, parking,
<br />park elements, kayak and canoe storage facilities, and views.
<br />● Provide traffic safety analysis, specifically regarding vision sight triangle and pedestrian crossings
<br />within the project limits. The analysis will be shown on site exhibits, at no more than four locations.
<br />● Develop overall irrigation master plan showing services, anticipated water meter sizes for ultimate
<br />project buildout
|