Lifecycle Replacement
<br />All park elements have a finite lifespan and will eventually
<br />require replacement. The lifecycle of each element varies
<br />based on its type, use, and environmental factors. Table
<br />5.2 identifies existing facilities currently in need of immediate
<br />lifecycle replacement to help the City identify urgent repairs and
<br />upgrades. Additionally, Table 5.3 provides cost estimates and
<br />lifecycle timelines for a wide range of park amenities, enabling
<br />the City to plan and budget for future replacement needs
<br />systematically. These costs are fine-tuned to the Bay Area and
<br />include installation.
<br />Program Replacement
<br />Timeline Unit Estimated Cost Notes
<br />Recreation Amenities
<br />Amphitheater 25-35 yrs Each $187,500-$375,000 Size varies based on seating needs
<br />Basketball Court 20-30 yrs Each $62,000-$93,000
<br />Baseball/Softball Field 25-30 yrs Each $221,680-$299,920 Infield mix only, incl. bleachers and
<br />fencing
<br />Backstop 20-30 yrs Each $68,000-$92,000
<br />Bocce Court 10-15 yrs Each $33,000-$66,000 12' x 60' court
<br />Community Garden 20-30 yrs Sq Ft $5-$10
<br />Disc Golf Course 10-20 yrs Each $1,100-$2,200 Cost per hole
<br />Dog Park 20-30 yrs Acre $630,000-$875,000 Includes surfacing, fencing, and agility
<br />features
<br />Fit Course 10-15 yrs Each $1,650-$2,750 Cost per equipment
<br />Multiuse Field - Artificial
<br />Turf 7-10 yrs Each $1,100,000-$1,650,000 Field only, size may vary
<br />Multiuse Field - Lawn 25-35 yrs Sq Ft $2-$4 Sod, irrigation
<br />Pickleball Court 10-20 yrs Each $110,000-$165,000 4 courts
<br />Playground 15-20 yrs Each $250,000-$1,100,000 Dependent on size and features
<br />Pump Track 10-20 yrs Each $20-$30 grading, trees, hydroseed, furnishing
<br />Roller Rink 20-30 yrs Each $22,000-$45,000 Asphalt surface with painted lines
<br />Skate Park 20-30 yrs Sq Ft $350-$800 In-ground
<br />Splash Pad 20-30 yrs Each $850,000-$1,150,000
<br />Tennis Courts 20-30 yrs Each $110,000-$165,000
<br />Volleyball 20-30 yrs Each $16,500-$27,500 Sand and nets
<br />TABLE 5.3 | Estimated Lifecycle Replacement Periods and Costs
<br />table continues on page 87
<br />TABLE 5.3 | Estimated Lifecycle Replacement Periods and Costs (continued)
<br />Program Replacement
<br />Timeline Unit Estimated Cost Notes
<br />Structures
<br />Aquatic Center 25-30 yrs Sq Ft $550-$825 Depends on pool type
<br />Concession Stand 20-30 yrs Sq Ft $450-$650
<br />Shade Sail 25-35 yrs Each $33,000-$110,000 Size varies
<br />Shade Structure 25-35 yrs Each $275,000-$550,000 20'x20' Structure
<br />Recreation Center 40-50 yrs Sq Ft $550-$650
<br />Restroom 20-30 yrs Each $385,000-$550,000 Multiple unisex single occupancy
<br />Furnishing
<br />Bench 15-20 yrs Each $1,500-$3,500
<br />Bike Rack 10-15 yrs Each $550-$1,650
<br />Bleachers 20-30 yrs Each $4,250-$5,750 5 row
<br />Barbeque 10-15 yrs Each $550-$1,650
<br />Drinking Fountain 10-15 yrs Each $13,500-$16,500
<br />Picnic Table 15-20 yrs Each $2,500-$5,500
<br />Trash Receptacle 10-15 yrs Each $2,000-$3,000
<br />Paving
<br />Trail (Unpaved)20-25 yrs Sq Ft $4-$6
<br />Trail (Paved)20-30 yrs Sq Ft $27-$45 Concrete Surface
<br />Asphalt Paving 20-30 yrs Sq Ft $6-$10
<br />Concrete Paving 20-30 yrs Sq Ft $20-$30
<br />Decomposed Granite
<br />Paving 20-30 yrs Sq Ft $13-$17
<br />Playground Surfacing -
<br />Wood Fiber n/a Sq Ft $8-$12
<br />Playground Surfacing -
<br />Rubber 7-10 yrs Sq Ft $32-$44
<br />Plaza Paving 20-30 yrs Sq Ft $25-$50 Stamped Concrete or Unit Pavers
<br />Lighting
<br />Court Lighting 25-35 yrs Each $48,000-$72,000
<br />Field Lighting 20-30 yrs Each $550,000-$1,000,000
<br />Pedestrian Light Pole 25-35 yrs Each $8,500-$11,500
<br />Plants
<br />Tree n/a Each $375-$750 Varies widely by tree type