<br /> 810 OPENING ENGINEER'S ESTIMATE McGuire and Hester Golden Bay Construction Sposeto Engineering, Inc.
<br /> DATE: Tuesday, February 6,2007 Date Approved 12/19/2006 9009 Railroad Avenue 3826 Depot Road 4301 Bettencourt Way
<br /> TIME: 3:00 P.M. Prepared by: AO Oakland, CA 94603 Hayward, CA 94545 Union City, CA 94587
<br />LOCATION: City Manager Large Conference Phone: (510) 632-7676 Phone: (510) 783-2960 Phone: (510)487-2424
<br /> Room Fax: (510) 562-5209 Fax: (510) 783-2971 Fax: (510) 487-6210
<br />ITEM
<br />NO. QUANTITY ITEM UNIT COST ITEM COST UNIT COST ITEM COST UNIT COST ITEM COST UNIT COST ITEM COST
<br />16 85 M Concrete Band at Median $45.00 $3,825.00 $57.00 $4,84500 $48.00 $4,080.00 $13500 $11,475.00
<br />17 620 M Remove and Replace (E) Chain $19000 $117,80000 $105.00 $65,100.00 $101.00 $62,620.00 $98.00 $60,760.00
<br /> Link Fence Along Golf Course
<br /> Sta. 16+75 to Sta. Sta. 22+95
<br />18 13 EA Raised Precast Concrete Palm $8,000.00 $104,000.00 $5,500.00 $71,500.00 $4,469.00 $58,097.00 $14,900.00 $193,700.00
<br /> Treet Planters, incl. Gravel Layer
<br />19 112 M2 Cobble Paving at Median $140.00 $15,680.00 $163.00 $18,256.00 $131.00 $14,672.00 $149.00 $16,688.00
<br />20 37 M2 Decomposed Granite at Median $86.00 $3,182.00 $6000 $2,220.00 $82.00 $3,034.00 $6600 $2,442.00
<br />21 410 M Header (2x4) $28.00 $11,480.00 $2100 $8,610.00 $29.00 $11,890.00 $4300 $17,630.00
<br />22 2,734 M3 Import Topsoil (40" deep) $55.00 $150,370.00 $46.00 $125,764.00 $46.00 $125,764.00 $47.00 $128,49800
<br />23 4,697 M2 Fine Grading $5.00 $23,485.00 $4.00 $18,788.00 $1.00 $4,697.00 $5.00 $23,485.00
<br />24 1 LS Automatic Irrigation $220,000.00 $220,000.00 $108,000.00 $108,000.00 $165,550.00 $165,550.00 $152,000.00 $152,000.00
<br />25 56 EA Plant 24" Box Trees $325.00 $18,200.00 $280.00 $15,680.00 $440.00 $24,640.00 $400.00 $22,400.00
<br />26 13 EA Palm Trees $8,000.00 $104,000.00 $4,650.00 $60,450.00 $3,575.00 $46,475.00 $3,500.00 $45,500.00
<br />27 1,134 EA Plan 5 gallon Shrubs $32.00 $36,288.00 $15.00 $17,010.00 $25.00 $28,350.00 $25.00 $28,350.00
<br />28 996 EA Plant 1 gallon Shrubs $15.00 $14,940.00 $9.00 $8,964.00 $11 .00 $10,956.00 $14.00 $13,944.00
<br />29 2,240 M2 Bark Mulch $4.00 $8,960.00 $400 $8,960.00 $3.30 $7,392.00 $4.30 $9,632.00
<br />30 1 LS 180 Day Plant Establishment & $10,000.00 $10,000.00 $12,000.00 $12,000.00 $8,800.00 $8,800.00 $10,000.00 $10,000.00
<br /> Maintenance
<br />31 1 LS Paint Existing Light Poles $51,000.00 $51,000.00 $17,250.00 $17,250.00 $19,800.00 $19,800.00 $15,000.00 $15,000.00
<br />32 1 LS Mobilization (5%) $92,206.91 $92,206.91 $115,00000 $115,00000 $294,000.00 $294,000.00 $150,000.00 $150,00000
<br /> TOTAL BASE BID $2,054,215.11 $1,652,350.00 $1,915,536.00 $2,297,417.00 ..
<br />BID ALTERNATE NO.1
<br />33 1 LS Remove and Replace Existing $58,000.00 $58,000.00 $52,880.00 $52,880.00 $48,116.00 $48,116.00 $110,000.00 $110,000.00
<br /> Chain-Linked Fences and Gates
<br /> and Install Landscaping on
<br /> Weset side of Doolittle Dr.
<br /> TOTAL BID ALTERNATE NO.1: $58,000.00 $52,88000 $48,116.00 $110,000.00