File Number: 16-175 <br />Appropriation <br />Account No. Amount <br />165-18-005 $225,000.00 <br />165-43-235 $ 54,001.81 <br />165-43-237 $116,983.00 <br />210-18-005 $ 95,000.00 <br />Total Appropriation $490,984.81 <br />Available funds for this project as of April 21, 2016 are as follows: <br />Account No. <br />165-18-005 <br />165-43-235 <br />165-43-237 <br />210-18-005 <br />Total <br />Amount <br />$196,176.82 <br />$ 17,108.64 <br />$116,983.00 <br />$ 94,741.44 <br />$425,009.90 <br />Total Estimated Cost of Project $449,940.00 <br />Design, Bid and Award Costs Already Spent $ 40,000.00 <br />Cost of Contract $339,950.00 <br />Remaining for Staff Costs and Contingency during Construction $ 45,059.90 <br />ATTACHMENT <br />Bid Summary <br />PREPARED BY: Nicole Noronha Castelino, Associate Engineer, Engineering and <br />Transportation Department <br />City of San Leandro Page 3 Printed on 5110/2016 <br />