BID SUMMARY
<br />BID OPENING
<br />DATE: March 17, 2021
<br />TIME: 3:00 p.m.
<br />LOCATION: City Clerk's Office
<br />ITEM
<br />NO.ITEM UNIT COST ITEM COST
<br />BASE BID
<br />1 Mobilization, Staging & Stockpiling per
<br />Sections 7-8.4 & 9-3.4
<br />1 LS $25,000.00 $25,000.00
<br />2 Temporary Traffic Control per Section
<br />600
<br />1 LS $30,000.00 $30,000.00
<br />3 Curb Ramp Review and Layout per
<br />Section 2-9
<br />76 EA $125.00 $9,500.00
<br />4 Install Curb and Gutter per City
<br />Standard Plan No. 100
<br />1806 LF $88.00 $158,928.00
<br />5 Install Wheelchair Curb Cut Ramp per
<br />City Standard Plan Nos. 106A and
<br />106B
<br />9856 SF $39.00 $384,384.00
<br />6 Install Sidewalk per City Standard Plan
<br />No. 100
<br />924 SF $28.00 $25,872.00
<br />7 Install Concrete Apron per City
<br />Standard Plan No. 114
<br />440 SF $45.00 $19,800.00
<br />8 Install Concrete Valley Gutter City
<br />Standard Plan No. 114
<br />490 SF $50.00 $24,500.00
<br />9 Install Asphalt Concrete Tie-ins per
<br />City Standard Plan Nos. 100 & 114
<br />1632 CF $40.00 $65,280.00
<br />10 Adjust Curb Drain Inlet Hood to Ramp
<br />Slope per Section 301-1.6
<br />1 EA $2,000.00 $2,000.00
<br />11 Relocate Roadside Sign and Post per
<br />Section 315
<br />2 EA $550.00 $1,100.00
<br />12 Relocate Roadside Sign on New Post
<br />per Section 315
<br />13 EA $650.00 $8,450.00
<br />QUANTITY
<br />PROJECT TITLE:Curb Ramp Upgrades 2021
<br />PROJECT NO.:
<br />BID NO.:
<br />ENGINEER'S ESTIMATE
<br />2021.0070
<br />20-21.012
<br />Prepared by: J. O'Driscoll
<br />Date Approved: 2/10/2021
<br />
<br />Rosas Brothers Construction Sposeto Engineering, Inc.Burch Engineering & Construction
<br />4731 Coliseum Way 4558 Contractors Place 180 Mendell Street
<br />Oakland, CA 94601 Livermore, CA 94551 San Francisco, CA 94124
<br />Phone: (510) 534-1077 Phone: (925) 443-4200 Phone: (415) 294-5100
<br />Fax: (510) 534-5077 Fax: (925) 443-6800 Fax: (415) 762-0170
<br />UNIT COST UNIT COST UNIT COST
<br />$10,000.00 $10,000.00 $14,000.00 $14,000.00 $50,000.00 $50,000.00
<br />$10,000.00 $10,000.00 $82,000.00 $82,000.00 $50,000.00 $50,000.00
<br />$400.00 $30,400.00 $475.00 $36,100.00 $150.00 $11,400.00
<br />$90.00 $162,540.00 $106.00 $191,436.00 $85.00 $153,510.00
<br />$40.00 $394,240.00 $29.00 $285,824.00 $55.00 $542,080.00
<br />$30.00 $27,720.00 $29.00 $26,796.00 $18.00 $16,632.00
<br />$45.00 $19,800.00 $30.00 $13,200.00 $15.00 $6,600.00
<br />$50.00 $24,500.00 $45.00 $22,050.00 $25.00 $12,250.00
<br />$32.00 $52,224.00 $51.00 $83,232.00 $11.00 $17,952.00
<br />$2,500.00 $2,500.00 $2,400.00 $2,400.00 $1,000.00 $1,000.00
<br />$400.00 $800.00 $450.00 $900.00 $500.00 $1,000.00
<br />$500.00 $6,500.00 $650.00 $8,450.00 $500.00 $6,500.00
<br />ITEM COST ITEM COST ITEM COST
<br />Bid Summary Curb Ramp Upgrades 2021.xlsx Page 4 of 6 Printed 3/19/2021 @ 11:12 AM103
|