<br />Subtask 4.1 – 65% PS&E <br />● Coordinate a Joint Resolution Team (JRT) meeting to review the 100% Design Development Plans <br />and Estimate <br />● Prepare response to the 100% DD comments on a JRT comment/ response matrix <br />● Coordinate all Bid package 1 work including: limits of work, temporary pedestrian access, <br />construction access, lagoon demo access, existing elements to remain, demolition, surcharging, <br />grading, utilities and services, future utility connections, and perimeter conforms for package 1 <br />● Identify VE options or Alternates for incorporation into the 65% PS&E <br />● Coordinate park elements with City staff and design team including: project phasing and timeline, <br />conform grading, site grading, accessible path of travel, surcharging, demolition phasing, drainage, <br />dredging (optional service), site access, construction staging zones, utility locations and connection <br />points, structural elements, fire, police, and garbage access, water and sewer services for buildings <br />and irrigation system, corrosion resistant finishes and materials, fencing, stormwater, traffic safety, <br />sight lines, and structural footings with design team <br />● Review, coordinate, and finalize all materials, finishes, colors, hardware, plumbing fixtures, lighting, <br />HVAC, penetrations, security locks, occupancy lighting, and locks for the prefabricated Restroom/ <br />Recreational Equipment building. <br />● Finalize all park materials including: paving, signage type, art elements, park amenities, site elements, <br />fencing, irrigation components, plant list, and City Standard Landscape elements <br />● Coordinate signage graphics and messaging with stakeholders <br />● Coordinate all in grade elements such as trees, light footings, fence footings, and buildings with all <br />underground utilities and clear zones <br />● Manage and Coordinate Existing Dry Utility work with PG&E to demolished: <br />○ Submit PG&E application for electric and gas service cut offs <br />○ Submit removal plan to existing telecommunication and fiber companies to disconnect service <br />○ Coordínate PG&E demo designs. PG&E/City Permitting coordinated by others. <br />○ Facilitate communication between utility rep and construction team regarding site logistics <br />● Provide geotechnical review of the 65% plans <br />● Manage and Coordinate New Dry Utility work with PG&E to develop: <br />○ (2) Service application and filing for all utilities <br />○ Design team meetings including PG&E meetings <br />○ Preparation of preliminary joint trench intent drawings and Form A <br />○ Distribution of preliminary joint trench plans to intended future utility service providers <br />○ Determine and indicate points of connection for all affected utilities and services <br />○ Identify utility vaults and substructures for dry utilities <br />○ Coordinate service points of connection or demarcation locations <br />○ Submittal of plans and comment responses to project team for coordination <br /> <br />● Updated 100% Design development plans to 65% construction documents and include additional <br />plans: <br />○ Horizontal Control Plans <br />○ Utility Plan & Profiles <br />○ Signage and Striping Plans <br />○ Dry Utility Plans